NEC has been used to deliver a small but critically important upgrade at the Port of Dover, the UK’s busiest international roll-on-roll-of (ro-ro) ferry port. Using an NEC3 Engineering and Construction Contract (ECC) Option A (priced contract with activity schedule), the £1.3 million works started in October 2022 and were completed on programme and budget in June 2023. Find out more: https://www.neccontract.com/projects/pier-f-bearing-replacement-port-of-dover-uk
Posted by farhaan.patel1 at 2025-04-28 15:00:43 UTC