Hong Kong's new saltwater supply system, completed six months early and on budget, provides toilet flushing water to over 11,000 homes in Sha Tin, New Territories. NEC's early warning process led to a realignment of the saltwater mains, which reduced disruption to the public and helped the project to be completed ahead of schedule. Clear risk sharing allowed the contractor to submit a more competitive tender price, while prompt resolution of NEC compensation events secured the cashflow of the local contractor.

Posted by NEC Contracts at 2024-11-05 07:00:02 UTC