NEC Users’ Group platinum member Network Rail utilized NEC contracts for a complex £249 million upgrade of Gatwick Airport Station in southern England. Costain and Systra were engaged under an NEC3 Professional Services Contract (PSC) for design and planning support in September 2016. The main NEC3 Engineering and Construction Contract (ECC) Option E was awarded to Costain in July 2019. Despite the challenges of working in a live railway and airport environment and through the Covid-19 pandemic, the project was completed within the revised schedule and budget in November 2023. #transport #airport #infrastructure #railway #station