Hi all, We are contractors on a ECSC and have a few queries with is current progress. Client issued a programme with tender docs and this was confirmed in the pre-let meeting. However due to client delays in preparation of our contracted works and acquiring street lighting for the areas the programme is now way behind original programme dates/phases. The original PM moved on and another put in place. He’s now issued an instruction to provide 4x our original resources, presumably to meet the original programme dates. Shouldn’t these periods of delay be added to the end dates? We have had no revised programme since the pre-let.

Posted by terry.dand at 2023-05-23 16:47:08 UTC