Please could anyone offer advice on the below: Contract-NEC3 Option C Target Cost Query- Defects corrected before completion are not a disallowed cost but how is the cost of damage to items other than the works, plant and material and equipment calculated? Basically a contractor hits a service whilst carrying out the works, this isn’t t technically a defect so should this be covered by the contractor’s insurance? Seems a grey area to my commercial team. Any advice would be greatly appreciated.
Posted by barkerdavid37 at 2023-01-24 15:23:35 UTC